混凝土密封固化剂施工方法
混凝土密封固化剂施工方法
Construction method of concrete seal curing agent
将基层表面清理干净、除去浮灰,油污等不利于粘结的物质;若为旧基层坑洼过多需预先补平;依施工面积计量好高渗透密封固化剂用量。
Clean up the surface of the base, remove the ash, oil pollution and other substances which are not good for bonding. If the old base pit is too much to be leveled in advance, the amount of the high permeability seal curing agent is measured in accordance with the construction area.
将高渗透密封固化剂均匀倒在地面上,自由流动渗透,同时可用抹子轻刮使整个地面均匀渗透;当基面渗透反应变得滑稠,用水雾湿润粘稠表面使高渗透密封固化剂继续渗透反应。
The high permeable seal solidifying agent is poured evenly on the ground, free flow and permeation, and the whole ground can be permeated evenly with the light scraping of the wipe; when the permeability of the base surface becomes thick, the high permeable seal solidifying agent will continue to permeate the permeation with water mist.
观察基面的密实程度和渗透状况,进行涂刷地面三遍及以上高渗透密封固化剂。
Observe the density and penetration of the base surface, and carry over three high permeable sealing hardener on the ground.
待基面渗透反应完全后(表面水分没有完全干燥为佳),使用专业的清洗地面机器,去清洗表面以及除去多余的材料。
After the basic surface permeation reaction is complete (the surface moisture is not completely dry), use the professional cleaning machine to clean the surface and remove the excess material.
在完工24小时后,用软毛抛光垫在地坪表面上抛光,需用树脂磨片对基面进行多次抛光处理。使用时间越长,光泽度越好。
After 24 hours of completion, the polishing pad is polished on the surface of the floor, and the polishing surface of the base surface is to be polished with resin grinding plates. The longer you use, the better the glossiness is.